QR-07A WRB / FLASHING #00838F ANCHOR DEVELOPMENT GROUP · GC #358732 · HVAC #365678 · ELEC #365679 ACCOUNTABLE: ENVELOPE CONTRACTOR qr.azanchordevelopment.com/w/qr-07a SCOPE WRB, exterior openings, flashing integration KEY RELEASE / HOLD POINT Drainage-plane continuity and photos STATUS (NO STEP MAY BE SKIPPED) PM OVERRIDE MUST BE DOCUMENTED 1. Draft 2. Not released 3. Ready 4. Active 5. QC hold 6. Inspection hold 7. Blocked 8. Ready for next trade 9. Released 10. Reopened 11. Closed FIELD DATA COMPANY ROC CLASS / LICENSE # VERIFIED FOREMAN PHONE BASELINE START BASELINE FINISH FORECAST START FORECAST FINISH ACTUAL START ACTUAL FINISH QTY BASIS / TARGET INSTALLED TO DATE PREDECESSOR SUCCESSOR BLOCKER BLOCKER OWNER / PROMISED DATE EVIDENCE REQUIRED BEFORE RELEASE AN UNCHECKED BOX IS NOT PROOF Inspection Photos Test report Checklist As-built BLOCKER → SUPERINTENDENT IMMEDIATELY PM IF CRITICAL-PATH OR UNRESOLVED NEXT SHIFT · CRITICAL SEVERITY = STOP WORK ADG-PROJECT-LOT-QR-07A-WRB-FLASHING-[AREA]-[PKG-REV] QR Job Board v2 Field-control interface only. Approved permit set, AHJ codes, approved changes and contracts govern.
QR-07A

WRB / FLASHING

PDF page 54

Waterproofing And Vapor Barriers

Waterproofing and vapor barrier requirements vary according to area. Check with the local building official about specific requirements and methods approved in that area.

1. PD Leaks in foundation or basement walls.

AT None.

CR Contractor should determine cause of leaks and make necessary repairs.

2. PD Leaks in conversation pit, or other areas designated to be constructed below floor level.

AT None.

CR Contractor should determine if leak is in foundation wall or chimney and make necessary repairs.

3. PD Leaks in gable end walls.

AT None.

CR Contractor should make necessary repairs.

4. PD Leaks through slump block walls.

AT None.

CR Contractor should make necessary repairs.

PDF pages 54-55

Weather Strip And Thresholds

1. PD Drafts around doors and windows.

AT Some infiltration of moisture and dust is normally noticeable around doors and windows, especially during high winds and heavy rain. Excessive infiltration resulting from open cracks, poorly fitted doors and windows or poorly fitted weather stripping is unacceptable.

CR The contractor should adjust or correct open cracks, poorly fitted doors or windows or poorly fitted weather stripping. If necessary, the contractor should adjust or replace the weather stripping or threshold one time during the first year of occupancy.

2. PD Threshold leaks water.

AT None.

CR Contractor should make necessary repairs.

3. PD Weather strips missing or damaged on windows.

AT None.

CR Contractor should make necessary repairs.

4. PD Excessive gap between doors at T astragal on double doors.

AT None.

CR Contractor should make necessary repairs.

5. PD Weather strip missing at T astragal.

AT None.

CR Contractor should make necessary repairs.