QR-11A FIRE ALARM #B71C1C ANCHOR DEVELOPMENT GROUP · GC #358732 · HVAC #365678 · ELEC #365679 ACCOUNTABLE: FIRE-ALARM CONTRACTOR qr.azanchordevelopment.com/w/qr-11a SCOPE Fire alarm, if applicable KEY RELEASE / HOLD POINT Approved fire plans, device / acceptance tests STATUS (NO STEP MAY BE SKIPPED) PM OVERRIDE MUST BE DOCUMENTED 1. Draft 2. Not released 3. Ready 4. Active 5. QC hold 6. Inspection hold 7. Blocked 8. Ready for next trade 9. Released 10. Reopened 11. Closed FIELD DATA COMPANY ROC CLASS / LICENSE # VERIFIED FOREMAN PHONE BASELINE START BASELINE FINISH FORECAST START FORECAST FINISH ACTUAL START ACTUAL FINISH QTY BASIS / TARGET INSTALLED TO DATE PREDECESSOR SUCCESSOR BLOCKER BLOCKER OWNER / PROMISED DATE EVIDENCE REQUIRED BEFORE RELEASE AN UNCHECKED BOX IS NOT PROOF Inspection Photos Test report Checklist As-built BLOCKER → SUPERINTENDENT IMMEDIATELY PM IF CRITICAL-PATH OR UNRESOLVED NEXT SHIFT · CRITICAL SEVERITY = STOP WORK ADG-PROJECT-LOT-QR-11A-FIRE-ALARM-[AREA]-[PKG-REV] QR Job Board v2 Field-control interface only. Approved permit set, AHJ codes, approved changes and contracts govern.
QR-11A

FIRE ALARM

The source PDF does not include a separate fire-alarm section; related electrical-system standards are included.

PDF pages 17-18

Electrical Systems

POTENTIALLY HAZARDOUS SITUATIONS SHOULD

1. PD Malfunctioning of electrical fixtures, switches or outlets.

AT None.

CR Contractor should make necessary repairs.

2. PD Breaker trips with normal use.

AT Breaker should operate as intended.

CR Contractor should replace defective breaker in accordance with manufacturer's warranty.

3. PD Electrical equipment not level, plumb and true.

AT None.

CR Contractor should make necessary repairs.

4. PD Electrical equipment or materials not secure or adequately supported.

AT None.

CR Contractor should make necessary repairs.

5. PD Switch located behind door.

AT All boxes for switches should be located on the side of the doorframe opposite the hinge.

CR Contractor should make necessary repairs.

6. PD Switches or plates span two different materials and are not flush.

AT Switches or plates should not span different types of building materials, vertically or horizontally, unless specified and then should be flush with both materials.

CR Contractor should make necessary repairs.

Source: 2024 Workmanship Standards for Licensed Contractors | PDF pages 17-18. Verify against current contract documents, approved plans, manufacturer requirements, and applicable code.