QR-15A DOORS / TRIM #6D4C41 ANCHOR DEVELOPMENT GROUP · GC #358732 · HVAC #365678 · ELEC #365679 ACCOUNTABLE: FINISH CARPENTER qr.azanchordevelopment.com/w/qr-15a SCOPE Interior doors, trim, hardware KEY RELEASE / HOLD POINT Fit, operation, hardware and protection STATUS (NO STEP MAY BE SKIPPED) PM OVERRIDE MUST BE DOCUMENTED 1. Draft 2. Not released 3. Ready 4. Active 5. QC hold 6. Inspection hold 7. Blocked 8. Ready for next trade 9. Released 10. Reopened 11. Closed FIELD DATA COMPANY ROC CLASS / LICENSE # VERIFIED FOREMAN PHONE BASELINE START BASELINE FINISH FORECAST START FORECAST FINISH ACTUAL START ACTUAL FINISH QTY BASIS / TARGET INSTALLED TO DATE PREDECESSOR SUCCESSOR BLOCKER BLOCKER OWNER / PROMISED DATE EVIDENCE REQUIRED BEFORE RELEASE AN UNCHECKED BOX IS NOT PROOF Inspection Photos Test report Checklist As-built BLOCKER → SUPERINTENDENT IMMEDIATELY PM IF CRITICAL-PATH OR UNRESOLVED NEXT SHIFT · CRITICAL SEVERITY = STOP WORK ADG-PROJECT-LOT-QR-15A-DOORS-TRIM-HARDWARE-[AREA]-[PKG-REV] QR Job Board v2 Field-control interface only. Approved permit set, AHJ codes, approved changes and contracts govern.
QR-15A

DOORS / TRIM

PDF pages 7-8

Carpentry - Finish - (Exterior)

Due to varying moisture conditions throughout Arizona, wood products will continue to expand and contract. This action is normal and beyond the contractor's control.

1. PD Crooked, warped fascias.

AT Excessively crooked or warped fascias are unacceptable.

CR Contractor should repair or replace one time within first year.

2. PD Wavy or improperly supported soffits.

AT Soffits should be reasonably straight, properly supported and nailed.

CR Contractor should make necessary repairs.

3. PD Trim omitted at juncture of soffit to wall when specified.

AT None.

CR Contractor should install proper trim per plans and specifications.

4. PD Shingle mold crooked, improperly nailed.

AT Shingle mold should follow line of fascia and be nailed securely to fascia.

CR Contractor should make necessary repairs.

5. PD Door casing, window casing or brick mold loose, out of square or does not fit.

AT Door, window trim and brick mold should fit, be square and securely attached.

CR Contractor should make necessary repairs.

6. PD Corner boards too short or loose.

AT Corner boards should be of proper length and securely attached.

CR Contractor should make necessary repairs.

7. PD Hammer marks on trim.

AT Un-repaired hammer marks are unacceptable.

CR Contractor should make necessary repairs.

8. PD Spliced barge rafters.

AT Long barge rafters may be spliced by approved methods, but splice should not separate or sag more than 1/8".

CR Contractor should make necessary repairs.

9. PD Exterior (including garage doors) warping, splintering, shrinking and exposing unfinished areas.

AT Exterior doors should be sealed on all six sides and finished per specifications.

CR Contractor should repair and refinish as necessary one time within the first year.

PDF pages 8-9

Carpentry - Finish - (Interior)

1. PD Poor workmanship on interior trim.

AT All joints on molding, casing, etc., should fit and be securely attached, as well as properly filled and sanded.

CR Contractor should make necessary repairs.

2. PD Pocket door rubs against frame or casing.

AT Door units should be installed square and plumb with proper guides, hang evenly in frame and work smoothly.

CR Contractor should adjust pocket door one time within the first year.

3. PD Bypass sliding doors uneven.

AT Bypass door units should be installed square and plumb with proper guides, hang evenly in frame and work smoothly.

CR Contractor should repair and/or adjust properly, one time within the first year.

4. PD Exposed nails on trim.

AT Nails on trim should be installed properly.

CR Contractor should make necessary repairs.

5. PD Doors bind or rub against jamb.

AT Doors should clear 1/8" at top and sides.

CR Contractor should make necessary repairs one time within first year.

6. PD Door will not stand open.

AT Doors should not move to open or closed when 45 degrees to opening.

CR Contractor should make necessary repairs.

7. PD Interior or exterior door warped.

AT Warping more than 1/4" when measured in any direction is unacceptable.

CR Contractor should replace warped door and finish to match existing doors one time within first year.

PDF pages 54-55

Weather Strip And Thresholds

1. PD Drafts around doors and windows.

AT Some infiltration of moisture and dust is normally noticeable around doors and windows, especially during high winds and heavy rain. Excessive infiltration resulting from open cracks, poorly fitted doors and windows or poorly fitted weather stripping is unacceptable.

CR The contractor should adjust or correct open cracks, poorly fitted doors or windows or poorly fitted weather stripping. If necessary, the contractor should adjust or replace the weather stripping or threshold one time during the first year of occupancy.

2. PD Threshold leaks water.

AT None.

CR Contractor should make necessary repairs.

3. PD Weather strips missing or damaged on windows.

AT None.

CR Contractor should make necessary repairs.

4. PD Excessive gap between doors at T-astragal on double doors.

AT None.

CR Contractor should make necessary repairs.

5. PD Weather strip missing at T-astragal.

AT None.

CR Contractor should make necessary repairs.

Code Compliance Revision 0.3 · Source-currentness recheck: September 30, 2026 · Controlled review checklist

This is a stand-alone code compliance checklist for this trade, added to the workmanship standards above and to full project-code requirements. It is not a complete trade code manual. It covers reviewed 2016–2026 changes and local implementation events; an older provision newly enforced locally is labeled as implementation, not claimed as newly invented code.

Job
Address / unit
Scope
Building / fire AHJ
Permit / edition / amendments
Approved-plan revision
Energy / green path
Applicable section / TIA / local amendment
Project-specific code verification by / date
Subcontractor / foreman
PM

Only affected new, replaced or altered work and legally triggered upgrades are included. The PM selects the applicable legal requirement and the compatible mandatory Anchor overlay before work starts. Unresolved source, limit or listing conflicts remain HOLD, and N/A requires a written reason. Checking a box means the item and its required evidence passed, not merely that it was read.

Where a city's legal minimum is lower, the compatible higher check remains an Anchor standard unless Cory approves a company-only exception. A city's nonadoption alone is not a reason to mark the higher company check N/A; actual scope, technical compatibility and legal/design/listing conflicts must be resolved.

Existing QR phases: QR-15A.

DT-01Glass guard top rail / handrail

Install the required attached top rail/handrail unless the accepted laminated-glass exception or design applies.

Change / applicability
2018 IRC R308.4.4 update. Affected: structural glass guard panels.
Required record
Glass certification, guard design and installed connections.
Hold point
Before guard use.

DT-02Guard-support framing

Confirm accepted edge-framing/anchorage accounts for guard loads, especially trusses/I-joists, before fastening finishes/hardware.

Change / applicability
2024 IRC R502.11 update. Affected: guards at affected floor edges.
Required record
Predecessor release, guard detail and connection photos.
Hold point
Before concealed anchorage / final use.

DT-03Stairway electric-lock release

Provide hardware capable of approved simultaneous unlocking without unlatching under specified command, alarm and power-failure conditions. Test jointly with controls/fire alarm.

Change / applicability
2024 IBC 403.5.3 / 1010.2.6 changes. Affected: applicable stair/high-rise electric door locks.
Required record
Hardware/locking plan and joint witness tests.
Hold point
Before door use / final release.

DT-04ESS utility-room doors

Install the accepted qualifying door with required self-latching/closing behavior and coordinate room protection. Ordinary hollow-core trim installation is not acceptance of the ESS barrier.

Change / applicability
2021 ESS expansion; 2024 IRC R330.4 current detail. Affected: ESS utility-space openings into the dwelling.
Required record
Approved door/room detail, product and closing/latching test.
Hold point
Before ESS release.

DT-05Composite-wood certification and labeling

Obtain compliant product/finished-goods labeling and supplier certification traceability. Do not accept only a generic “green” claim or treat all structural plywood/solid wood as regulated composite wood.

Change / applicability
Federal compliance began June 1, 2018; TSCA Title VI labeling transition after March 22, 2019. Affected: regulated hardwood plywood, MDF/thin-MDF or particleboard in doors, trim and built-in finish products containing regulated composite wood; screen product/manufacture/import dates and exemptions.
Required record
Label photo, supplier invoice, product/lot and applicable certification/exemption evidence.
Hold point
Before purchasing or installing affected material.

DT-06Weighed construction-waste diversion

Segregate and document eligible door/trim construction waste toward the project requirement of at least 50% eligible nonhazardous C&D waste diverted by weight. Exclude excavated soil/land-clearing debris and do not count alternative daily cover or waste-to-energy as diversion.

Change / applicability
2023 Scottsdale mandatory green-code implementation, not a claim the provision first existed in 2023. Affected: applicable commercial/multifamily green-code scope; resolve the local < 5,000-sq-ft project exception and any higher Anchor requirement.
Required record
Weight tickets, material/destination, recycling/reuse receipts and PM project diversion calculation.
Hold point
Before trade closeout; keep records throughout work.

Evidence and Release Record

ItemResult: Pass / Fail / N/A / Not verifiedRequired value / observed result / evidenceSub initials / datePM verification / date
DT-01Not verified
DT-02Not verified
DT-03Not verified
DT-04Not verified
DT-05Not verified
DT-06Not verified

Unverified or failed applicable items block the stated hold point. The subcontractor certifies actual work and evidence; the PM independently verifies and releases after required official inspections. Cory approves only company-standard exceptions, never statutory, permit, design or listing waivers.

Subcontractor certification / date
PM release / date
AHJ / special inspection
Open correction / approved N/A / Anchor-only exception

Applicability Appendix

Record the exact adopted section/amendment, applicable exception, design/product instruction and required test configuration for each item before starting. A model-edition change is not automatically local law, and a local rule exported to another city is an Anchor requirement only when technically compatible and accepted.

This section does not establish an exhaustive all-clause ten-year history or every-city strictness proof. No unverified change is used as a passing criterion; current-only provisions with no demonstrated decade change remain in the full existing acceptance packet rather than falsely appearing here as new changes.

The September 30, 2026 recheck refreshed cited source evidence. A historical source can verify a change without establishing its current local applicability; source recheck is not a project release or a complete clause-by-clause supersession certification.

Sources: 2024 Workmanship Standards for Licensed Contractors | PDF pages 7-55; Door, Trim and Guard Contractor Code Compliance Rev 0.3 (rechecked 2026-09-30). Verify against current contract documents, approved plans, manufacturer requirements, and applicable code.