QR-18P PLUMBING TRIM #303F9F ANCHOR DEVELOPMENT GROUP · GC #358732 · HVAC #365678 · ELEC #365679 ACCOUNTABLE: PLUMBING CONTRACTOR qr.azanchordevelopment.com/w/qr-18p SCOPE Plumbing trim and startup KEY RELEASE / HOLD POINT Leak / function / final inspection STATUS (NO STEP MAY BE SKIPPED) PM OVERRIDE MUST BE DOCUMENTED 1. Draft 2. Not released 3. Ready 4. Active 5. QC hold 6. Inspection hold 7. Blocked 8. Ready for next trade 9. Released 10. Reopened 11. Closed FIELD DATA COMPANY ROC CLASS / LICENSE # VERIFIED FOREMAN PHONE BASELINE START BASELINE FINISH FORECAST START FORECAST FINISH ACTUAL START ACTUAL FINISH QTY BASIS / TARGET INSTALLED TO DATE PREDECESSOR SUCCESSOR BLOCKER BLOCKER OWNER / PROMISED DATE EVIDENCE REQUIRED BEFORE RELEASE AN UNCHECKED BOX IS NOT PROOF Inspection Photos Test report Checklist As-built BLOCKER → SUPERINTENDENT IMMEDIATELY PM IF CRITICAL-PATH OR UNRESOLVED NEXT SHIFT · CRITICAL SEVERITY = STOP WORK ADG-PROJECT-LOT-QR-18P-PLUMBING-TRIM-[AREA]-[PKG-REV] QR Job Board v2 Field-control interface only. Approved permit set, AHJ codes, approved changes and contracts govern.
QR-18P

PLUMBING TRIM

PDF pages 24-25

Plumbing

1. PD Leakage from any soil, waste, vent, gas or water piping.

AT None.

CR Contractor should make necessary repairs.

2. PD Faucet or valve leak.

AT No valve or faucet should leak due to defects in material or workmanship. Leakage caused by worn washers is considered owner maintenance except during manufacturer's warranty period.

CR Contractor should repair or replace the leaking faucet or valve unless due to owner negligence.

3. PD Defective plumbing fixtures or trim fittings.

AT None.

CR Contractor should replace or repair defective fixture or fitting according to manufacturer's warranty unless workmanship is involved, then contractor should repair problem. Contractor is not responsible for failure due to owner negligence or water impurities.

4. PD Stopped up sewers and drains.

AT None.

CR Contractor should be responsible if caused by workmanship.

5. PD Plumbing fixture loose at floor.

AT None.

CR Contractor should repair as necessary.

6. PD Vents or other penetrations located in roof valley.

AT Vents or other penetrations should not be located within 18" of valley centerline.

CR Contractor should relocate vents or other penetrations and have roof repaired by properly licensed contractor.

Code Compliance Revision 0.3 · Source-currentness recheck: September 30, 2026 · Controlled review checklist

This is a stand-alone code compliance checklist for this trade, added to the workmanship standards above and to full project-code requirements. It is not a complete trade code manual. It covers reviewed 2016–2026 changes and local implementation events; an older provision newly enforced locally is labeled as implementation, not claimed as newly invented code.

Job
Address / unit
Scope
Building / fire AHJ
Permit / edition / amendments
Approved-plan revision
Energy / green path
Applicable section / TIA / local amendment
Project-specific code verification by / date
Subcontractor / foreman
PM

Only affected new, replaced or altered work and legally triggered upgrades are included. The PM selects the applicable legal requirement and the compatible mandatory Anchor overlay before work starts. Unresolved source, limit or listing conflicts remain HOLD, and N/A requires a written reason. Checking a box means the item and its required evidence passed, not merely that it was read.

Where a city's legal minimum is lower, the compatible higher check remains an Anchor standard unless Cory approves a company-only exception. A city's nonadoption alone is not a reason to mark the higher company check N/A; actual scope, technical compatibility and legal/design/listing conflicts must be resolved.

Existing QR phases: QR-04P, QR-08, QR-18P.

PL-01Grease-interceptor upstream slope

Provide uniform slope of at least 1/4 in. per ft under the applicable IPC basis rather than a generic larger-pipe minimum.

Change / applicability
2018 IPC 704.1 addition. Affected: horizontal piping upstream of a grease interceptor.
Required record
Diameter/run/location and measured slope.
Hold point
Before backfill or cover.

PL-02Water-closet reduction exceptions

Verify any size reduction is one of the expressly allowed fittings/arrangements. Do not extend the exception to arbitrary downstream reductions.

Change / applicability
2018 IPC/IRC clarification. Affected: specified water-closet flange/bend/offset arrangements.
Required record
Fitting IDs, routing and accepted detail.
Hold point
Before cover.

PL-03Relief-discharge insert fittings

Use discharge tubing one nominal size larger than the relief outlet and secure the outlet end, with all other adopted discharge/product requirements satisfied.

Change / applicability
2018 IPC 504.6 update. Affected: applicable relief-valve tubing installed with insert fittings.
Required record
Outlet/tubing sizes, fitting data and discharge photos.
Hold point
Before final plumbing release.

PL-04Water-heater pan material

Use the approved pan/drain detail and reject a plastic pan beneath a gas-fired water heater.

Change / applicability
2018 IPC 504.7 update. Affected: storage-water-heater leakage locations needing a pan.
Required record
Fuel/heater model, pan product and drain detail.
Hold point
Before heater startup.

PL-05New potable-treatment / backflow provisions

Verify contamination-safe equipment location, required air-gap waste terminations and the device-specific backflow standard. Obtain NSF 61 evidence for regulated potable tank coatings/linings.

Change / applicability
2018 IPC 608 additions. Affected: potable treatment tanks, dispensers and humidifiers.
Required record
Device/standard schedule, certificates and installation photos.
Hold point
Before cover / startup.

PL-06Fixture distribution and single-user signage

Install the approved fixture distribution/signage, including single-user use-by-either-sex designation and proportional lavatory distribution where required. Use the accepted occupant-load/facility calculation.

Change / applicability
2018 IPC 403 changes. Affected: applicable commercial/public toilet-room work.
Required record
Approved fixture-count plan, installed count/location and signage.
Hold point
Before final release.

PL-07Plastic DWV vacuum test option

Select the approved safe test method. Under reviewed 2024 IRC text the vacuum option is −5 psi / negative 10-in. mercury for 15 min without further evacuation, and positive air testing is not thereby permitted for plastic.

Change / applicability
2024 plumbing-code testing update. Affected: plastic DWV rough tests under an accepted code/material procedure.
Required record
Selected code/product procedure, calibrated gauge and witnessed time/result.
Hold point
Before backfill / cover.

PL-08Expansive-soil support and plastic sewer tracing

Install the accepted code/designer-specific support and tracer detail, with exact material and geometry populated before procurement. No pass based on an unspecified “tracer installed” claim.

Change / applicability
2024 IPC updates. Affected: buried piping/plastic sewer runs.
Required record
Exact adopted section/detail, product identifiers and pre-backfill evidence.
Hold point
Before backfill.

PL-09Hot-water pipe route length

Check the approved route against the new 100-ft maximum length rule and any stricter local demand-delivery requirements.

Change / applicability
2021 IRC P2905.3 addition. Affected: applicable hot-water distribution to fixtures.
Required record
Diameter/run map, developed lengths and approved delivery design.
Hold point
Before cover.

PL-10Local water-efficiency and demand recirculation

Verify WC ≤ 1.28 gpf, shower aggregate ≤ 2.0 gpm at 80 psi and private lavatory ≤ 1.5 gpm at 60 psi, with kitchen and specialty exceptions separately scheduled. Screen demand-recirculation thresholds by actual largest diameter/run rather than install an uncontrolled loop.

Change / applicability
Scottsdale 2023 local-code implementation. Affected: new/replaced residential fixtures and hot-water distribution under accepted local/company scope.
Required record
Rated fixture schedule and exceptions; diameter/length map; insulation/control test.
Hold point
Before procurement, cover and trim release.

PL-11Assigned additional-efficiency measure

Install the assigned energy measure exactly as scheduled and document its rating, geometry and control. Do not substitute a component or delete a measure used to satisfy the approved package/credits without written design acceptance.

Change / applicability
2021 additional-package requirement; 2024 prescriptive credit-system update. Affected: new/altered water-heating/distribution measure included in the accepted energy design. This is not a blanket untouched-system upgrade.
Required record
Approved path and assigned measure, product rating / installed value, design acceptance for substitutions.
Hold point
Before procurement and before concealment / final release.

Evidence and Release Record

ItemResult: Pass / Fail / N/A / Not verifiedRequired value / observed result / evidenceSub initials / datePM verification / date
PL-01Not verified
PL-02Not verified
PL-03Not verified
PL-04Not verified
PL-05Not verified
PL-06Not verified
PL-07Not verified
PL-08Not verified
PL-09Not verified
PL-10Not verified
PL-11Not verified

Unverified or failed applicable items block the stated hold point. The subcontractor certifies actual work and evidence; the PM independently verifies and releases after required official inspections. Cory approves only company-standard exceptions, never statutory, permit, design or listing waivers.

Subcontractor certification / date
PM release / date
AHJ / special inspection
Open correction / approved N/A / Anchor-only exception

Applicability Appendix

Record the exact adopted section/amendment, applicable exception, design/product instruction and required test configuration for each item before starting. A model-edition change is not automatically local law, and a local rule exported to another city is an Anchor requirement only when technically compatible and accepted.

This section does not establish an exhaustive all-clause ten-year history or every-city strictness proof. No unverified change is used as a passing criterion; current-only provisions with no demonstrated decade change remain in the full existing acceptance packet rather than falsely appearing here as new changes.

The September 30, 2026 recheck refreshed cited source evidence. A historical source can verify a change without establishing its current local applicability; source recheck is not a project release or a complete clause-by-clause supersession certification.

Sources: 2024 Workmanship Standards for Licensed Contractors | PDF pages 24-25; Plumbing Contractor Code Compliance Rev 0.3 (rechecked 2026-09-30). Verify against current contract documents, approved plans, manufacturer requirements, and applicable code.